At a glance
OPG is advancing fish habitat enhancement on the Wanapitei River as part of the Coniston and Stinson GS Redevelopment Project, which will modernize both hydro facilities.
Following site visits and discussions with Indigenous communities, fish habitat cribs have been identified as the preferred enhancement approach.
Indigenous engagement remains central to the project, with ongoing collaboration with Wahnapitae and Atikameksheng Anishnawbek First Nations.
OPG employees and members of Atikamesksheng and Wahnapitae First Nations are pictured during a site visit.
In northeast Ontario, OPG is redeveloping two of its oldest hydroelectric stations while working with Indigenous communities to support fish habitat along the Wanapitei River.
The 121-year-old Coniston and 101-year-old Stinson Generating Stations (GS) near Sudbury are being modernized to help provide 12 MW of clean, reliable power for decades to come.
As part of the work, OPG’s Indigenous Working Group recently visited sites upstream of Stinson GS with representatives from Wahnapitae and Atikameksheng Anishnawbek First Nations to explore fish habitat enhancement opportunities.
The group considered several restoration options, including spawning habitat, artificial reefs, shoreline revegetation and reconnecting waterways. Fish habitat cribs — artificial structures that create shelter and habitat for fish — were identified as the preferred approach. The work could also provide a meaningful opportunity for community involvement.
Ongoing engagement remains central to the projects. OPG meets weekly with both communities, while land guardians visit the sites every two weeks and share observations from the field.
During the visit, the group also observed local wildlife and heard stories from Al, an Elder, about fishing on the waterway, including memories of catching large walleye.
The team is aiming to finalize enhancement specifications this fall, with implementation anticipated as a community initiative in winter 2027 or 2028.

The redevelopment of Coniston and Stinson will include replacing the powerhouses at both sites, installing two modern turbine generators at each station, and adding new mechanical and electrical systems.
More stories
OPG exploring new generation opportunities
A new era begins at Pickering Nuclear
A welder by trade, a teacher at heart

© 2026 Ontario Power Generation Inc. All Rights Reserved.